After the groundbreaking ceremony took place in spring 2019, the extension was accepted on schedule in July 2020. Shortly after completion, the SMT and administrative areas were relocated.
The SMT production area on the ground floor of the building extends over 600 m². The area offers enough space for the existing systems and also provides capacities for expanding the machine park.
In addition to a large warehouse for semi-finished goods, the first floor also houses the secretariat, the offices of the project management assistants, the project managers, the accounting department, the operations manager, the managing director and three meeting rooms. All rooms are equipped with the most modern air conditioning and ventilation systems and offer a high level of working comfort.
The upper floors one and two can be reached with an elevator from the ground floor. The ground floor and the first floor are connected to the existing building by a bridge.